The Steinhaus Hall Exterior Demo Project is fast approaching with the work scheduled to begin on March 22 and be completed by March 30, 2008.
The following is recommended:
- All personal items be packed and taken home for safekeeping prior to March 22.
- Notebooks, journals, books and any objects on your shelves be removed prior to demo work due to vibrations and possible dust from construction.
Bio Sci Facilities will provide the following for each window office located on the 2nd, 3rd and 4th floors on Thursday , February 28, 2008:
- Boxes - qty. 5 (initially)
- Labels
- Packing material , bubble wrap and/or plastic wrap
(Should you require additional boxes please contact the Help Desk [x4-8085, Pam Atkins]).
Boxed items from your shelves may:
- Remain in the office
- Stored by Bio Sci Facilities
- Relocated to your assigned temperature space (move dates pending at this time).
If you would like your packed books, journals, etc., stored by Bio Sci Facilities, please contact the Help Desk/Pam Atkins (x4-8085) and provide the following information:
- Name
- Room No.
- Qty of boxes to be stored (all boxes must be labeled)
Materials readily available for Faculty/Staff;
- Boxes, labels
- Bubble Wrap, plastic
- Foam (for computers)
As a reminder, the 'Demo Project' only affects the window offices of the 2nd, 3rd and 4th floors of Steinhaus Hall.
Thank you for your cooperation and patience!
Bio Sci Facilities
| To: |
Steinhaus Hall Occupants |
| From: |
Robyn Stiffler |
|
Director of Bio Sci Facilities |
| Date: |
February 20, 2008, 3:00 pm |
| Location: |
NSI Room 1114 |
| Subject: |
Steinhaus Hall Occupants - SH Phase II Town Meeting |
| |
|
| |
Hello Everyone,
I am happy to announce that Design & Construction Services will be hosting an information/town meeting on February 20 at 3:00PM in NS I room 1114. The goal of this meeting is to provide additional information about the upcoming "demo" phase of this project. Phase II "demo" is planned to commence on March 22, with the work scheduled to be complete by March 30, 2008.
Design & Construction Services will discuss the "scope of work", construction schedule, and address any concerns that the faculty and or staff may have regarding the SH Wall Repair project.
If I have missed someone from the list above, please invite him or her to attend the information/town meeting on February 20, at 3:00 PM.
If you have any questions or concerns, I can be reached x4-8284.
Thank you in advance for your patience,
Robyn Stiffler
Director of BioSci Facilities
(949) 824-8284 - Office |
Changes in the Use of BBQ's on Campus
To Occupants of Natural Sciences 1: Sustainable and Green Campus Initiatives
I am writing to inform you that the Monitoring Based Commissioning Project for Sprague, Gillespie, and Natural Sciences 1 will be kicking off this week. We will be walking the buildings the on March 28 with our consultant EMC Engineers. Have no fear Commissioning will not affect the buildings occupants. The team from EMC will be conducting air pressure test, taking readings from various thermostats, and monitoring other building systems over the next several months. There may also be the occasional ladder with someone inspecting equipment in the ceiling. If any concerns are generated that can not be addressed with a simple explanation of who, or what is taking place please feel free to contact me at x4-9309. McGaugh and Berkeley Place showed great energy savings from the very same study and we expect similar savings on these buildings. This work is all part of the Sustainable and Green Campus initiatives.
Thanks,
Matt Gudorf
Matt Gudorf
Project Manager
University of California, Irvine
201A Interim Office Building
Irvine, CA 92697-5444
(949) 824 - 9309 office
(949) 824 - 1744 fax
(949) 241 - 2360 mobile
Key Issuance News
Key Issuance for Developmental and Cell Biology rooms
has been transferred to the departmental office. The Dev and Cell
office is located in McGaugh Hall, room 5205. If you have
questions regarding key issuance for Dev and Cell rooms please contact
the department staff at 4-5347 or call Bio-Sci Facilities at
4-8812.
Key Issuance for MB & B rooms
has been transferred to the departmental office. The MB & B
office is located in McGaugh Hall, room 3205. If you have
questions regarding key issuance for MB & B rooms please
contact
the department staff at 4-4739 or call Bio-Sci Facilities at
4-8812.
|